-
About Elsaco
-
Projects
-
Elsaco Companies
-
Communication
-
Human resources
-
Contact
ADDRESS
Elsaco Electronic
41A Pacea Str.
710 013, Botoșani
RomâniaTel. +40 231 507 060
Fax: +40 231 532 905
Case Studies
ENERGY PROJECTS
Combined Heat and Power
| Project title | “Design and execution of works to achieve the investment objective for the project Source of thermal and electrical energy production through high-efficiency cogeneration” |
| Client | Vâlcea County |
| Duration | 2025-2027 |
| Value | 607 million lei, without VAT |
Activities:
• design;
• works execution;
• tests and commissioning.
Key elements:
• 5 internal combustion engine units, operating on natural gas (52 MWe and 45 MWt);
• 4 hot water boilers (100 MWt);
• heat accumulator;
• heating medium pumping station;
• chemical water treatment station;
• thermal degasser for the preparation of make-up water;
• electrical station for connecting generators;
• premises connections and networks.
| Project title | “Source of thermal and electrical energy production through high-efficiency cogeneration in Constanța municipality” |
| Beneficiary | Constanța Municipality |
| Duration | 2024-2026 |
| Value | 581 million lei |
Activities:
• design;
• works execution;
• tests and commissioning.
Key elements:
- nominal thermal capacity of at least 160 MWt:
- cogeneration plant: 5 units with internal combustion thermal engine, operating on natural gas, with an individual capacity of approx. 10.4 MWe + 9 MWt, in a flexible configuration which allows the use of green hydrogen mixed with natural gas;
- auxiliary thermal energy production facility: 4 hot water boilers with an individual capacity of 25 MWt, 2 steam boilers with a capacity of 12 t/h, in a flexible configuration which allows the use of green hydrogen mixed with natural gas;
- thermal degassing and additional water pumping station in the district heating network;
- heat accumulator;
- thermal agent pumping station related to thermal energy production facilities;
- set of water boreholes to feed the water treatment plant;
- electric generator connection station;
- connections and networks in the premises.
| Project title | “Source of heat and electricity production through high-efficiency cogeneration at CET Hidrocarburi SA” |
| Beneficiary | Arad Municipality |
| Duration | 2024-2026 |
| Value | 397 million lei, without VAT |
Activities:
• design;
• works execution;
• tests and commissioning.
Key elements:
• total capacity: approx. 138 MWt + 31.5 MWe;
• cogeneration plant: 3 CHP units operating on natural gas mixed with green hydrogen, with an individual capacity of approx. 10.2 MWt + 10.5 MWe;
• separate thermal energy production facility: 4 hot water boilers with an individual capacity of 25 MWt, a steam boiler with a capacity of 12 t/h, operating on natural gas mixed with green hydrogen;
• thermal degassing station and water injection into the SACET primary thermal network, with a maximum capacity of 50 m3/h;
• heat accumulator with hot water storage capacity of approx. 8,500 m3;
• heating agent pumping station for the SACET primary heating network, with a maximum capacity of 4,000 m3/h, equipped with 4 variable speed pumps.
Heating systems
District Heating Network Rehabilitation – Phase VI, Constanţa
| Project title | “Completion of the Rehabilitation of the Primary District Heating Networks and Continuation of the Rehabilitation Works on the Secondary District Heating Networks and Heat Substations in the Municipality of Constanța” |
| Beneficiary | Constanța Municipality |
| Duration | 2026-2029 |
| Value | 222 million lei |
Activities:
•design and obtaining all required permits, approvals, and authorizations;
•construction and installation works;
•testing and commissioning.
Key Elements:
• rehabilitation of 0.29 km of primary district heating network route, corresponding to 0.58 km of district heating transmission (primary) pipelines;
• rehabilitation of 18.8 km of network route, corresponding to approximately 70 km of secondary district heating distribution pipelines for heating, hot water, hot water recirculation, serving 23 heat substations;
• rehabilitation of equipment in 37 heat substations;
• rehabilitation and modernization of the SCADA system.
Rehabilitation of the District Heating Main Network in the Municipality of Arad
| Project title | “Rehabilitation of the District Heating Transmission Main Network in the Municipality of Arad” |
| Beneficiary | Arad Municipality |
| Duration | 2025-2028 |
| Value | 186,9 million lei |
Activities:
• design;
• construction and installation works, including:
o pipeline replacement;
o rehabilitation of existing transmission mains;
o optimization of district heating network routes;
o digitalization of the district heating transmission system;
• testing and commissioning.
Key Elements:
• replacement of 19,445 m of primary district heating network route, corresponding to approximately 38,890 m of supply and return pipelines;
• implementation of a monitoring, alarm, and automation system enabling continuous supervision of the network’s condition and rapid identification of potential failures;
• rehabilitation of four main transmission mains and two interconnecting sections through insulation restoration, covering approximately 4.47 km of network route.
Rehabilitation of the heating system in Focșani – Stage III
| Project title | “Rehabilitation of the urban heating system in Focșani municipality for the period 2009-2028 in order to comply with environmental legislation and increase energy efficiency – stage III” |
| Beneficiary | Focșani Municipality |
| Duration | 2024-2026 |
| Value | 54,1 million lei |
Activities:
- technical project with execution details and documentation for the Construction Authorization;
- execution of works and commissioning of the installations:
- rehabilitation of 7,270 km of primary heating network pipes (3,635 km route of primary heating network sections * 2 return pipes);
- rehabilitation of 26,850 km of secondary heating network pipes (7,170 km route of secondary heating networks);
- rehabilitation of constructions, thermomechanical and automation works for 6 Thermal Points;
- tests and commissioning;
- operator personnel training.
Rehabilitation of the heating system in Bucharest – Lot 1
| Project title | “Rehabilitation of the heating system of Bucharest municipality – Lot 1” |
| Beneficiary | Bucharest Municipality |
| Duration | 2022-2026 |
| Value | 300 million lei, without VAT |
Activities:
Design and execution for the rehabilitation of the primary heating network related to Lot 1 Magistrala II SUD:
• decommissioning of existing pipes and cleaning the thermal gallery;
• rehabilitation of the thermal gallery and tanks;
• installation of isolation valves in existing tanks;
• execution of electric connection fireplaces;
• execution and installation of fixed and mobile supports, installation of pre-insulated pipes;
• welding works, sleeves, insulation works, fittings;
• pressure tests;
• installation and commissioning of the breakdown monitoring system;
• installation of data transmission cable and line units.
Rehabilitation of the heating system in Bucharest – Lot 2
| Project title | “Rehabilitation of the heating system of Bucharest municipality – Lot 2” |
| Beneficiary | Bucharest Municipality |
| Duration | 2022-2026 |
| Value | 168 million lei, without VAT |
Activities:
Design and execution for the rehabilitation of the heating network related to the Grozăvești main heating network II-III:
• decommissioning of existing pipelines;
• installation of isolating valves in existing tanks;
• execution and installation of fixed and mobile supports;
• welding works, sleeves, insulation works, fittings;
• pressure tests;
• connecting the signaling wires between the pipe sections and checking their continuity;
• installation of the data transmission cable.
Rehabilitation of secondary thermal networks, stage IV – Constanţa
| Project title | “Rehabilitation of secondary thermal networks, stage IV – Constanța”” |
| Beneficiary | Constanța Municipality |
| Duration | 2024-2026 |
| Value | 117,5 million lei, without VAT |
Activities:
• design;
• acquisition of materials and equipment;
• execution of works;
• commissioning the installations;
Key elements:
• rehabilitation of 23.255 km of thermal distribution/secondary network route, related to 12 thermal points.
Rehabilitation of the heating system in Bucharest – Lot 5
| Project title | “Rehabilitation of the heating system of Bucharest municipality – Lot 5” |
| Beneficiary | Bucharest Municipality |
| Duration | 2022-2026 |
| Value | 77.9 million lei, without VAT |
Activities:
Design and execution for the rehabilitation of the heating network related to the following main heating networks – II South; II-III Grozăvești; V Grozăvești; Progresu-Berceni; II West; I-II-III West:
• decommissioning of existing pipelines;
• installation of isolating valves in existing tanks;
• execution and installation of fixed and mobile supports;
• welding works, sleeves, insulation works, fittings;
• pressure tests;
• connecting the signaling wires between the pipe sections and checking their continuity;
• installation of the data transmission cable.
Modernization of thermal energy system – Gheorgheni, Harghita
| Project title | Modernization of the thermal energy supply system of the municipality of Gheorgheni |
| Beneficiary | Gheorgheni Municipality |
| Duration | 2022-2025 |
| Value | 15.5 million lei, without VAT |
| Role | General Contractor |
Activities:
• design and execution of rehabilitation and expansion works for 2.2 km of thermal transport network route;
• the modernization of 41 thermal modules, by installing new fully automated thermal modules;
• testing and commissioning (PIF).
HYDRO PROJECTS
Capture, treatment and distribution of drinking water
Water sources and water supply works – Târgu Jiu
| Project title | Design and execution of water sources and water supply works in Târgu Jiu (Runcu, Vâja-Clocotiș, Sohodol, Șușița) |
| Beneficiary | ApaRegio Gorj |
| Duration | 2025-2027 |
| Value | 53 million lei |
Activities:
• technical design services;
• construction works;
• supply and installation of technological machinery and equipment;
• works for automation and data transmission in the SCADA system;
• testing and commissioning.
Water supply – treatment Călărași
| Project title | Oxidation station in the Chiciu pretreatment station. Rehabilitation of Aduction wire 2 “Chiciu – Călărași” on the Undercrossing sector of the Siderurgic Canal. Chlorination station in the Călărași treatment plant. Rehabilitation of the Vișinii source and adduction pipeline. Rehabilitation of SP Vișinii. New treatment station and new Vișinii water tank. Vișinii-Potcoava transport pipeline. New Potcoava water household. Source, adduction, treatment plant and water tank for the Fundulea zonal system |
| Beneficiary | ECOAQUA S.A. CĂLĂRAŞI |
| Duration | 2024-2027 |
| Value | 74 million lei |
| Role | Leader of association |
Activities:
• design;
• construction works (rehabilitation of water intakes, chlorination stations; construction of pre-oxidation station, treatment stations, chlorination stations, establishment of water management, sludge management, water supply tanks, replacement of pumps, tanks, transport pipes, pumping group, etc.);
• supply and installation of machinery and technological equipment;
• automation and data transmission works in local SCADA and regional SCADA;
• testing and commissioning.
| Project title | Equipping the drinking water treatment plants of Slatina Municipality with filters for drinking water |
| Beneficiary | S.C. Compania de Apă Olt S.A. |
| Duration | 2021-2025 |
| Value | 51.8 million lei, without V.A.T. |
| Role | Leader of association |
Activities:
• rehabilitation and extension of Nicolae Bălcescu and Salcia treatment plants: endowment with high-performance equipment for treatment and monitoring of drinking water quality.
Key elements:
• maximum daily flow of 540 m3/h – Nicolae Bălcescu treatment and pumping station;
• maximum daily flow of 490 m3/h – Salcia treatment plant.
Irrigation works
Rehabilitation of the South Razelm irrigation system, Tulcea county
| Project title | Rehabilitation of the South Razelm irrigation system, Tulcea county |
| Client | National Agency for Land Improvements – ANIF |
| Duration | 2023-2026 |
| Value | 110 million lei |
| Role | General Contractor |
Activities:
• rehabilitation and retrofit of the pumping stations SPA 6 Martie and the repumping station SRPA 1 – 6 Martie;
• rehabilitation of water supply and distribution channels CA0, CA1 and CA2;
• rehabilitation of related hydrotechnical constructions.
Rehabilitation of the main irrigation infrastructure B.H. Călmăţui, Brăila county
| Project title | Rehabilitation of the main irrigation infrastructure B.H. Călmățui, Brăila county |
| Client | National Agency for Land Improvements – ANIF |
| Duration | 2020-2025 |
| Value | 42.4 million lei, without VAT |
| Role | General Contractor |
Activities:
- modernization of the irrigation infrastructure;
- construction works and hydromechanical installations;
- rehabilitation of electrical installations.
Key elements:
- flow rate pumping station SRPA 1+3: 59.400 m3/h;
- flow rate pumping station SRP 4: 44.280 m3/h.
AUTOMATION AND SCADA PROJECTS
| Project title | Design and implementation of a centralized SCADA system |
| Client | SC APA PROD Deva SA |
| Duration | 2025-2027 |
| Value | 24,5 million lei, without VAT |
Activities:
• design and implementation of a centralized SCADA system;
•supply of equipment and software licenses;
•testing and commissioning.
Key elements:
• three main modules:
o Central SCADA Control Center – Wastewater Treatment;
o Central SCADA Control Center – Water Treatment;
o Central SCADA Control Center – Water Supply and Sewer Networks.
• establishment of the Central Control Center and Local Control Centers;
• PLC applications for the automation of technological processes;
• SCADA applications for centralized monitoring and control of facilities;
• configuration, installation, and commissioning of the hardware and software infrastructure;
• IT infrastructure management and monitoring solutions;
• centralized data backup and recovery solution;
• virtualization platform to ensure service continuity;
• cybersecurity solutions, including security incident management and vulnerability management;
• physical security systems, including intrusion detection systems, video surveillance, and fire detection/alarm systems.
| Project title | GIS and SCADA Unitary System operating and implementation software |
| Client | Vital SA Baia Mare |
| Duration | 2025-2028 |
| Value | 16,9 million lei, without VAT |
Activities:
• integration of existing objectives into the SCADA system;
• implementation of Videowall systems;
• optimization of data transfer between the GIS platform and the SCADA system;
• training of VITAL personnel who will operate the system.
Automation, electrical installations and SCADA system development/implementation – Galaţi
| Project title | Automation, electrical installations and SCADA system development/implementation |
| Client | Apă Canal S.A. Galați |
| Duration | 2018-2025 |
| Value | 3.4 million lei, without VAT |
Under the contract will be performed:
– designing and executing works for automation, electrical installations;
– SCADA Regional Water System development / implementation in the Galați county operating area;
– SCADA Regional Sewerage System development / implementation in the Galați county operating area;
The project aims at carrying out works in water and wastewater infrastructure in 22 territorial administrative units in Galați county, including the municipalities of Galaţi and Tecuci and the town of Bereşti.
